Production planning models for a refractory production system
Call Number: AIT RSPR no. IE-85-15 Material type:
SeriesSeries: Asian Institute of Technology. Research studies project report ; no. IE-85-15Publication details: Bangkok : Asian Institute of Technology, 1985Description: 1 v. (various pagings)Subject(s): Online resources: Dissertation note: Research Studies Project Report (M. Eng.) - Asian Institute of Technology, 1985 Summary: This research study covers all production planning requirements for Refractory Plant . It includes production scheduling , raw material requirements planning, manpower planning, and plant capacity planning. Actually, these models are divided to three levels for different purpose of planning . The short-term plan is the lowest level to find the exact schedule of production . The medium-term plan is the level of preparing facilities for short-term plan. The long-term plan is for predicting the future and preparing facilities for the future. The scheduling model is a simulation model using real data . The medium-term and long-term production models are aggregate production model (APP) using linear programming technique to solve the problems. The manpower planning model uses a heuristic model to choose the best schedule of workers and number of workers required for each machine . The material requirements planning model use results of APP and the modification of MRP to solve the problem. The plant capacity planning is a part of APP model.
| Cover image | Item type | Current library | Home library | Collection | Shelving location | Call number | Materials specified | Vol info | URL | Copy number | Status | Notes | Date due | Barcode | Item holds | Item hold queue priority | Course reserves | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
20-AIT Publication
|
Asian Institute of Technology Library AIT Publications | AIT RSPR no. IE-85-15 (Browse shelf(Opens below)) | 1 | Available | 30050003110631 | |||||||||||||
20-AIT Publication
|
Asian Institute of Technology Library AIT Publications | AIT RSPR no. IE-85-15 (Browse shelf(Opens below)) | 2 | Available | 30050003110623 | |||||||||||||
40-Archives
|
Asian Institute of Technology Library Archives | AIT RSPR no. IE-85-15 (Browse shelf(Opens below)) | Available | 30050160109749 |
A research study submitted in partial fulfillment of the requirements for the degree of Master of Engineering, School of Engineering and Technology
Research Studies Project Report (M. Eng.) - Asian Institute of Technology, 1985
This research study covers all production planning requirements for Refractory Plant . It includes production scheduling , raw material requirements planning, manpower planning, and plant capacity planning. Actually, these models are divided to three levels for different purpose of planning . The short-term plan is the lowest level to find the exact schedule of production . The medium-term plan is the level of preparing facilities for short-term plan. The long-term plan is for predicting the future and preparing facilities for the future. The scheduling model is a simulation model using real data . The medium-term and long-term production models are aggregate production model (APP) using linear programming technique to solve the problems. The manpower planning model uses a heuristic model to choose the best schedule of workers and number of workers required for each machine . The material requirements planning model use results of APP and the modification of MRP to solve the problem. The plant capacity planning is a part of APP model.
There are no comments on this title.

AI Search