Prediction versus actual response of rocks in excavation of underground cavern at Lam Ta Khong Pumped Storage Project
- Bangkok : Asian Institute of Technology, 1998
- 261 leaves : ill.
- Thesis ; no. GE-97-23 .
- Asian Institute of Technology. Thesis ; no. GE-97-23 .
A thesis submitted in partial fulfillment of the requirements for the degree of Master of Science, School of Civil Engineering
Thesis (M.Sc.) - Asian Institute of Technology
The excavation and rock response of a large underground cavern (25 m x 49 m x 175 m in dimension) of the Lam Ta Khong Pumped Storage Project in siltstone and sandstone was studied. The cavern was excavated with drill and blast and supported with rock anchors, rockbolts, steel fiber reinforced shotcrete. Actual geology and rock response during various stages of excavation was reviewed and compared with the prediction. Comparison was made between rock mass quality classified according to EPDC and RMR classifications. Predominant rock response consisted of slaking and minor stress slabbing and loosening. Actual ground movement in roof and walls were compared with the pre-construction and post-construction predicted by FEM and BEM numerical analyses, and it was found that they were in good agreement.
Rock mechanics Lam Ta Khong Project Underground construction